Toowoomba Water Treatment Plant Upgrade
Successful Completion of Overflow Lagoons Construction Project at Toowoomba Water Treatment Plant
Project
scope
– Bulk and Detailed Earthworks
– Placement of a geo-synthetic clay liner with detailed cappingÂ
– Installation of several Gabion rock mattresses
– Installation of a 1050 diameter storm water pipe run
– Installation of electrical and communication pit and pipe
– Rock breaking
Everest Civil is delivering the project with a 20 tonne excavator, fitted
with integrated GPS, tilt hitch and a highly experienced operator, to achieve a detailed design tolerance and high standard of delivery exceeding expected project timelines.
execution
Client
Fulton Hogan
Services
Civil Construction and Plant Hire
Location
Mt Kynoch, Toowoomba
Dates
20/10/2022 to 30/05/2023
Sector
Water